Freiston Road works in Boston to restart after water repairs
Work to rebuild Freiston Road in Boston restarts in the week of 23 November, with a daytime closure for up to a week.
· 1 min read · Magna Newsroom

Work to rebuild Freiston Road in Boston will restart in the week beginning 23 November, after a pause to let Anglian Water fix two leaks.
The road will be closed during the day, from 9am to 3pm, for up to a week. The diversion runs via Church Road, Skirbeck Road, South End and the A16.
The scheme is rebuilding the road between the Spilsby Road junction and the Church Road and Vauxhall Road junction, using around 1,300 tonnes of material.
Lincolnshire County Council says the work shows its Street Works Charter in action, with the council and Anglian Water, the first utility company to sign the charter, working together to cut disruption.